Stage 5 Statement of Compliance issued; settlements commence july. 26 jun
Stage 6 civil practical completion certified by council. 20 jun
Stage 7 pavements commenced; program holding to october PC. 17 jun
PCG #33 held; minutes issued to the portal. 12 jun
Display village licence drafting instructed. 6 jun
FY27 sales budget adopted — 20 lots per month carried. 3 jun
Stage 4 civil tender list — approval of invited contractors.
response due 11 jul 26
FY27 marketing program — budget paper circulated.
response due 16 jul 26
Display village head licence — heads of terms for review.
response due 25 jul 26
| Stage | Total | Settled | Sold | Avail | Future |
|---|---|---|---|---|---|
| 1 | 31 | 31 | — | — | — |
| 2 | 57 | 57 | — | — | — |
| 3 | 50 | 48 | 2 | — | — |
| 5 | 56 | — | 51 | 5 | — |
| 5B | 12 | — | 12 | — | — |
| 6 | 48 | — | 29 | 19 | — |
| 7 | 40 | — | 10 | 30 | — |
| 4 | 12 | — | — | — | 12 |
| 1A | 8 | — | — | — | 8 |
| Total | 314 | 136 | 104 | 54 | 20 |
| Stage | FLP Approval | Construction Drawings | Civil Commence | Council PC | Statement of Compliance | Titles | Previous Forecast (MMM-YY) |
|---|---|---|---|---|---|---|---|
| 1 | 9-Oct-23 | 14-Jun-24 | 8-Jul-24 | 20-Mar-25 | 6-May-25 | 19-May-25 | May-25 |
| 2 | 20-Feb-24 | 14-Jun-24 | 22-Jul-24 | 9-Apr-25 | 23-May-25 | 5-Jun-25 | Jun-25 |
| 3 | 6-Mar-24 | 28-Jun-24 | 12-Aug-24 | 21-May-25 | 1-Jul-25 | 14-Jul-25 | Jul-25 |
| 5 | 19-Aug-24 | 14-Oct-24 | 4-Nov-24 | 18-Mar-26 | 29-Apr-26 | 12-May-26 | May-26 |
| 5B | 19-Aug-24 | 14-Oct-24 | 4-Nov-24 | 18-Mar-26 | 29-Apr-26 | 12-May-26 | May-26 |
| 6 | 28-Aug-24 | 11-Nov-24 | 2-Dec-24 | 27-May-26 | 10-Jul-26 | 21-Aug-26 | Aug-26 |
| 7 | 18-Sep-24 | 13-Dec-24 | 9-Feb-26 | 16-Oct-26 | 27-Nov-26 | 30-Nov-26 | Nov-26 |
| 4 | 12-Sep-26 | 6-Nov-26 | 1-Feb-27 | 24-Sep-27 | 5-Nov-27 | 18-Nov-27 | Nov-27 |
| 1A | 12-Sep-26 | 20-Nov-26 | 15-Mar-27 | 22-Oct-27 | 3-Dec-27 | 17-Dec-27 | Dec-27 |
0 — | |||||||||||||
| jul-26 | aug-26 | sep-26 | oct-26 | nov-26 | dec-26 | jan-27 | feb-27 | mar-27 | apr-27 | may-27 | jun-27 | FY27 | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Net movement | −2.1 | −2.4 | +3.2 | +4.4 | +2.3 | −1.2 | +5.6 | +4.1 | +2.6 | −2.0 | −1.8 | −0.4 | +12.3 |
| Cumulative position | −2.1 | −4.5 | −1.3 | +3.1 | +5.4 | +4.2 | +9.8 | +13.9 | +16.5 | +14.5 | +12.7 | +12.3 | +12.3 |
| Ref | Action | Due | Status |
|---|---|---|---|
| A-112 | Stage 5 settlement program — booking schedule to conveyancers | 4 jul | in hand |
| A-114 | Stage 6 titles — SoC lodgement pack preparation | 11 jul | in hand |
| A-109 | Display village licence — heads of terms to client | 25 jul | with client |
| A-116 | Stage 4 civil tender — documentation assembly | 22 jul | scheduled |